Simulation · Minimal Organization · Energy and water

Electricity grid operator

A grid operator as a walkable model: see how a solar system or heat pump gets connected and when grid planning becomes the bottleneck.

Trailer

NETZ VELMERAU and all its quantities are invented. Fitted to your grid, the model shows things that appear on no single map today – such as real connection requests per local grid or the loading of your secondary substations.

How does the grid connection of a solar system or heat pump work? The fictional grid operator NETZ VELMERAU shows the process step by step. It connects everyone who asks, keeps the grid running around the clock and rebuilds it at the same time for heat pumps and solar.

The path of a connection request: an installer registers a solar system on the portal, small systems take the simplified route, larger ones go to grid planning for a load flow study, the approval goes out with a timetable, a contractor reinforces the grid where needed, then come meter exchange and register entry. Target in the model: timetable within eight weeks.

In a heat pump boom, grid planners become the bottleneck. Standardised connection packages take work off them, and remote-controlled substations let the control centre switch faster. The page is aimed at management, grid planning, operations, the control centre, metering and regulatory management.

A solar system or heat pump is to be connected

  1. 01

    Installer submits the request: An installer registers a solar system with storage on the portal.

  2. 02

    Grid connection checks the request: Small systems pass the simplified route, larger ones go to load flow.

  3. 03

    Installer submits missing documents: The installer submits the data sheet.

  4. 04

    Grid planning checks compatibility: Grid planning calculates: can the local feeder take the feed-in?

  5. 05

    Approval with timetable: The approval goes out, with timetable and conditions.

  6. 06

    Contractor reinforces the grid: A contractor lays a stronger cable.

  7. 07

    Installer reports completion: The installer builds the system and reports completion.

  8. 08

    Appointment at the customer: An appointment for the meter exchange is arranged.

  9. 09

    Meter exchange: Metering installs a bidirectional meter.

  10. 10

    Register and feed-in payment: Check against the market master data register, payment starts.

  11. 11

    Connected.

A site at work

01

A site at work

7 buildings, 14 departments, about 1,300 staff: in the evening light golden arcs show who reports to whom.

Every floor opened up

02

Every floor opened up

Every building can be opened, floor by floor – right into single rooms such as ‘Grid control centre’, with workplaces and people at work.

What is shown – why – for whom

What is shown Why For whom
Diagram ‘Where it gets tight’ in a heat pump boom Whyshows grid planning at its limit For whomManagement, grid planning
Diagram ‘What each control does’: connection packages, grid planners, remote-controlled substations Whyranks the levers for faster connections For whomManagement, regulatory management
Diagram ‘The path across the site’: control centre, substations, depot Whyshows the routes taken during faults For whomGrid operations, control centre
Diagram ‘Where the time goes’: grid connection and substation Whyshows where eight weeks pass and where years pass For whomInstallers, municipalities
Diagram ‘Who sits where – and reports to whom’ Whyshows locations and responsibilities For whomOnboarding
Disruption ‘Storm’ with the process ‘A medium-voltage cable fails’ Whyshows fault location and repair under pressure For whomControl centre, crisis team
Process ‘A smart meter is installed’ Whysets the rollout against the number of fitters For whomMetering
Who works with whom

03

Who works with whom

‘Asset management’ with all 6 relations: Grid planning, Construction and project delivery, Maintenance, Regulatory management and Grid control centre – and outside Municipalities (concession, right of way).

A solar system or heat pump is to be connected

04

A solar system or heat pump is to be connected

A single case can be followed – step by step, with the waiting time at every station. Target: timetable within eight weeks.

Films from the model

  • The building opens up

    Just before sunset the floors drift apart – ‘Administration and customer centre’ opens up as the camera rises and circles the building until night falls.

  • Who reports to whom, who works with whom

    Blue hour above the site: first the golden arcs of the structure, then the collaboration of the most connected department, finally the whole building.

  • A day in time-lapse

    From ten in the morning to midnight in 26 seconds: the sun moves, the windows light up, at night the data lines glow.

  • Surge and system outage

    In time-lapse: ‘Storm’ brings more work, then ‘Grid control system fails’ – the data arcs turn red. The control ‘Standardised connection packages’ set to ‘many’ brings recovery.

  • Seven diagrams

    Calculated live from the model: ‘Who works with whom’, ‘Year, week, day’, ‘Management levels as a staircase’, ‘How a case flows’, ‘What each control does’, ‘What the work depends on’, ‘Where it gets tight’.

  • Using the software

    With the full interface: open a building, a department’s relations, ‘Storm’, a control, diagrams with their panel, one case.

Departments in the model

  • Management

    Leads the grid company – independently of the group's sales.

  • Compliance officer (non-discrimination)

    Ensures all suppliers are treated equally.

  • Asset management

    Owner role: strategy, investment, condition of assets.

  • Grid planning

    Load flow, target grid, (n-1): optimise first, then reinforce, then expand.

  • Regulatory management

    Calculates costs and revenues for the regulator.

  • Grid control centre

    Around the clock: switching, managing outages, planning outages.

  • Fault service

    On standby: drives out, locates, repairs.

  • Maintenance

    Maintains substations, stations and lines.

  • Construction and project delivery

    Builds lines, stations and substations.

  • Grid connection

    Checks requests for solar systems, heat pumps and charging points.

  • Customer service and outage hotline

    Takes reports and informs during outages.

  • Metering

    Installs meters and smart metering systems.

  • Network economics

    Network charges, market communication, feed-in payments.

  • IT and control technology

    Grid control system, geodata, meter data – isolated.

Grid control system fails

05

Grid control system fails

The data arcs turn red and work stalls – the simulation shows where cases pile up and how long recovery takes.

06

A day in 26 seconds

From ten in the morning to midnight in time-lapse: commuters, moving light, windows switching on – and at night the data lines.

All processes in the model

A solar system or heat pump is to be connected

  1. 01Installer submits the request: An installer registers a solar system with storage on the portal.
  2. 02Grid connection checks the request: Small systems pass the simplified route, larger ones go to load flow.
  3. 03Installer submits missing documents: The installer submits the data sheet.
  4. 04Grid planning checks compatibility: Grid planning calculates: can the local feeder take the feed-in?
  5. 05Approval with timetable: The approval goes out, with timetable and conditions.
  6. 06Contractor reinforces the grid: A contractor lays a stronger cable.
  7. 07Installer reports completion: The installer builds the system and reports completion.
  8. 08Appointment at the customer: An appointment for the meter exchange is arranged.
  9. 09Meter exchange: Metering installs a bidirectional meter.
  10. 10Register and feed-in payment: Check against the market master data register, payment starts.
  11. 11Connected.

A medium-voltage cable fails

  1. 01Protection trips, alarm in the control room: A cable breaks down, protection trips. In the control room the section lights up red.
  2. 02Switch remotely: The control centre isolates the section and resupplies the rest via the ring.
  3. 03Hotline and fault service run in parallel.
  4. 04Outage hotline and outage page: The hotline takes calls, the outage page shows the area.
  5. 05Fault service drives out: The fault service drives to the station.
  6. 06The team is on site.
  7. 07Locating the cable fault: A test van locates the fault in the cable.
  8. 08Emergency generator or temporary fix: An emergency generator supplies the last customers.
  9. 09Contractor digs up: A contractor digs up the street.
  10. 10Fitting a cable joint: Fitters install a cable joint.
  11. 11Switch back to normal state: The control centre switches back to the normal state.
  12. 12Documentation for outage statistics: The fault goes into the statistics.
  13. 13Fixed.

A substation is built

  1. 01Need from the grid expansion plan: Grid planning sees: in the west capacity no longer suffices for heat pumps and charging points.
  2. 02Investment approval: Asset management approves the investment.
  3. 03Assess costs under regulation: Regulatory management assesses: will the costs be recognised?
  4. 04Permit and transformer run in parallel.
  5. 05Permit: The authority approves the substation.
  6. 06Order transformer (lead time): The transformer is ordered.
  7. 07Approved, transformer on its way.
  8. 08Construction: switchgear, protection, cables: Switchgear, protection and cables are built.
  9. 09Control centre plans the outages: The control centre plans which lines are switched off for the tie-in.
  10. 10Commissioning, entry into the control system: The substation goes into operation and appears on the grid display.
  11. 11In operation.

A smart meter is installed

  1. 01Plan installation: Metering plans the installation at a household with a heat pump.
  2. 02Appointment at the customer: Appointment at the customer.
  3. 03Meter exchange: The fitters install meter and gateway.
  4. 04Set up and connect the gateway: The gateway is set up and securely connected.
  5. 05Installed.

How a grid operator can use the model

  • Internal communication

    Control centre, three substations, grid depot, yard and administration on one site. Asset management, operations and connections see how their processes interlock – from request to fault.

    For whomManagement, communications, all divisions

  • Onboarding

    ‘Who sits where – and reports to whom’ shows locations and responsibilities. New staff see which department takes over when, for a connection request or a cable fault.

    For whomNew staff in connections, operations and metering

  • Training

    Apprentices trigger ‘Storm’ and follow ‘A medium-voltage cable fails’: alarm, remote switching, fault location, excavation, cable joint, switching back to normal.

    For whomElectrical apprentices, work-study students, fault crews

  • Explaining to installers and municipalities

    Installers and local councils see where eight weeks pass and where years pass, as with a new substation. ‘Where the time goes’ makes the difference clear without jargon.

    For whomConnections team, customer service, municipalities, installers

  • Strategic overview

    Connection packages, more grid planners, remote-controlled substations and the pace of the smart meter rollout side by side. ‘What each control does’ ranks the levers for faster connections.

    For whomManagement, regulatory management, asset management

Diagrams from the model

07

Diagrams from the model

‘Who works with whom’ as a dome of arcs – one of 14 diagrams calculated live from the same data.

The whole software

08

The whole software

Situation, key figure, time-lapse, six views, controls and disruptions: one click on a department shows its task, location and all relations.

What you can change

Controls

  • Connection requests: Subsidy schemes make requests jump.
  • Standardised connection packages: More requests take the simplified route, grid planning is relieved (model assumption).
  • Grid planners: How many load flow studies run at once.
  • Remote-controlled substations: The control centre switches faster (model assumption).
  • Smart meter rollout: More installations tie up the same fitters.

Disruptions

  • Storm: For a day trees fall into lines: twenty times as many faults, location and repair take longer.
  • Excavator damages a cable: For two hours faults pile up in a construction area.
  • Grid control system fails: For two hours the control centre cannot switch remotely.
  • Transformer shortage: For a year transformers take even longer.

What the model gives a grid operator

  • 01

    The bottleneck has a name

    Set connection requests to heat pump boom and the queue at grid planning visibly grows – and a tip at the bottleneck names the control that relieves it.

  • 02

    Operating and expanding at once

    Connection, cable fault, substation build and smart meter installation run in parallel. More installations tie up the same fitters, and the model shows where that gets tight.

  • 03

    Faults with routes

    In a storm, ‘The path across the site’ shows the fault crews moving between control centre, depot and substations.

  • 04

    Supply chains in view

    The ‘Transformer shortage’ disruption stretches the substation build. It shows what a year of extra lead time means for grid expansion.

  • 05

    For committees and big screens

    A browser is enough, and large projections work too – so the model can be shown in council committees, at installer events or in your own lobby.

  • NETZ VELMERAU in the morning – low sun, long shadows, the first commuters on their way in.
    NETZ VELMERAU in the morning – low sun, long shadows, the first commuters on their way in.
  • 7 buildings, 14 departments, about 1,300 staff: in the evening light golden arcs show who reports to whom.
    Administration and customer centre in evening light – golden arcs show who reports to whom.
  • Just before eight – people stream from the car park and the street into the buildings.
    Just before eight – people stream from the car park and the street into the buildings.
  • Blue hour – the windows of NETZ VELMERAU light up.
    Blue hour – the windows of NETZ VELMERAU light up.
  • At night from above – Administration and customer centre opened up, data lines glowing across the site.
    At night from above – Administration and customer centre opened up, data lines glowing across the site.
  • Administration and customer centre opened up – every floor with workplaces and people.
    Administration and customer centre opened up – every floor with workplaces and people.
  • Dusk, performance view – rings of light show how busy each department is.
    Dusk, performance view – rings of light show how busy each department is.
  • Looking into the floor of Asset management – rows of desks, the floors above as outlines of light.
    Looking into the floor of Asset management – rows of desks, the floors above as outlines of light.
  • Every building can be opened, floor by floor – right into single rooms such as ‘Grid control centre’, with workplaces and people at work.
    A room of its own – Grid control centre.
  • Substation North opened up – every floor with workplaces and people.
    Substation North opened up – every floor with workplaces and people.
  • Substation South – all floors at once, performance view.
    Substation South – all floors at once, performance view.
  • Structure at dusk – golden arcs from every floor to the buildings reporting to it.
    Structure at dusk – golden arcs from every floor to the buildings reporting to it.
  • ‘Asset management’ with all 6 relations: Grid planning, Construction and project delivery, Maintenance, Regulatory management and Grid control centre – and outside Municipalities (concession, right of way).
    Collaboration – Asset management with all 6 relations – to departments, buildings and partners.
  • Data flows at night – systems and users linked by glowing lines.
    Data flows at night – systems and users linked by glowing lines.
  • Data flows at dusk – which department uses which system.
    Data flows at dusk – which department uses which system.
  • Structure across the whole site – reporting lines between the buildings.
    Structure across the whole site – reporting lines between the buildings.
  • The whole network at night – collaboration inside and far beyond.
    The whole network at night – collaboration inside and far beyond.
  • A single case can be followed – step by step, with the waiting time at every station. Target: timetable within eight weeks.
    Every step labelled – name, how many are waiting, utilisation.
  • Following one case – ‘A solar system or heat pump is to be connected’ – step by step through the building.
    Following one case – ‘A solar system or heat pump is to be connected’ – step by step through the building.
  • Storm – resources view, the backlog grows floor by floor.
    Storm – resources view, the backlog grows floor by floor.
  • The data arcs turn red and work stalls – the simulation shows where cases pile up and how long recovery takes.
    Grid control system fails – the data arcs turn red, work stalls.
  • The lever – Standardised connection packages set to ‘many’ – a flash shows where it acts.
    The lever – Standardised connection packages set to ‘many’ – a flash shows where it acts.
  • Spring at NETZ VELMERAU – Administration and customer centre opened up, rings show the workload.
    Spring at NETZ VELMERAU – Administration and customer centre opened up, rings show the workload.
  • Summer evening – warm light, long shadows, golden arcs above the square.
    Summer evening – warm light, long shadows, golden arcs above the square.
  • Autumn – leaves on the paths, performance view.
    Autumn – leaves on the paths, performance view.
  • Winter evening – snow on the site, Administration and customer centre open and lit, collaboration glowing.
    Winter evening – snow on the site, Administration and customer centre open and lit, collaboration glowing.
  • ‘Who works with whom’ as a dome of arcs – one of 14 diagrams calculated live from the same data.
    Diagram ‘Who works with whom’, calculated live from the model.
  • Diagram ‘Year, week, day’, calculated live from the model.
    Diagram ‘Year, week, day’, calculated live from the model.
  • Diagram ‘Management levels as a staircase’, calculated live from the model.
    Diagram ‘Management levels as a staircase’, calculated live from the model.
  • Diagram ‘How a case flows’, calculated live from the model.
    Diagram ‘How a case flows’, calculated live from the model.
  • Diagram ‘What each control does’, calculated live from the model.
    Diagram ‘What each control does’, calculated live from the model.
  • Diagram ‘What the work depends on’, calculated live from the model.
    Diagram ‘What the work depends on’, calculated live from the model.
  • Diagram ‘Where it gets tight’, calculated live from the model.
    Diagram ‘Where it gets tight’, calculated live from the model.
  • Diagram ‘Who leads whom’, calculated live from the model.
    Diagram ‘Who leads whom’, calculated live from the model.
  • The whole software – situation, key figure, time, views and the controls below.
    The whole software – situation, key figure, time, views and the controls below.
  • Administration and customer centre selected – floor list on the right, the floors drift apart.
    Administration and customer centre selected – floor list on the right, the floors drift apart.
  • Situation, key figure, time-lapse, six views, controls and disruptions: one click on a department shows its task, location and all relations.
    Asset management – card with task, location and all relations.
  • Storm triggered – timeline, key figure and bottleneck react.
    Storm triggered – timeline, key figure and bottleneck react.
  • Countering – Standardised connection packages increased – the tile shows the effect since the change.
    Countering – Standardised connection packages increased – the tile shows the effect since the change.
  • Diagram ‘How a case flows’ with its panel – findings in sentences.
    Diagram ‘How a case flows’ with its panel – findings in sentences.
  • Diagram ‘Who works with whom’ with its panel.
    Diagram ‘Who works with whom’ with its panel.
  • Follow a case – step, waiting time and target on the card.
    Follow a case – step, waiting time and target on the card.
  • The tour leads through the software in eight steps.
    The tour leads through the software in eight steps.
  • 36 organisations to choose from, each with its own picture.
    36 organisations to choose from, each with its own picture.

Your grid as a model

Want to show your connection process, your control centre or your grid expansion? We talk about your data and goals. For a first impression you get the password to the simulation from us – just ask.

Request the password if you are interested →

Ask about this

Minimal Organization: Stromnetzbetreiber

What you enter goes to this site alone and serves only to answer you.

Basis and limits

Fictional grid operator · model based on researched industry structures · no forecast for real companies

1 case = 1 connection request, 1 fault, 1 substation or 10 smart meters · 1 figure ≈ 25 employees

All volumes, durations, rates and capacities are model assumptions, not values of a real grid operator.

Here the target counts as met when the installer has the timetable; construction and meter exchange follow.

Documented: timetable for connection requests within eight weeks, reporting of interruptions over three minutes, unbundling from sales.

Public sources the model is based on:

  • Energiewirtschaftsgesetz (u. a. §§ 7, 7a, 11, 14a, 14d, 52)
  • Bundesnetzagentur: Monitoringbericht
  • Netzentwicklungsplan Strom (NOVA-Prinzip)
  • Anreizregulierungsverordnung
  • Erneuerbare-Energien-Gesetz § 8

Similar business models

← Minimal Organization

NETZ VELMERAU and all its quantities are invented. Fitted to your grid, the model shows things that appear on no single map today – such as real connection requests per local grid or the loading of your secondary substations.